Oceanwide Project

Update: March 31, 2017

Buildings 40 and 50 have been demolished to the ground floor level and there will be no further overhead demolition work. Thank you for your patience as we reached this significant milestone in the project.

This Saturday, Oceanwide's contractors will be working at 50 1st Street from 7:00 AM - 4:30 PM. Beginning Monday and continuing for the rest of the week, the hours of this work will be extended from 7:00 AM - 8:00 PM.

Starting Thursday, March 30th, mobilization will begin on the Mission Street site to prepare for the shoring of existing utility vaults adjacent to the site. This work will include setting up concrete pumps and mobilizing additional crane and drill equipment. Starting the week of April 3rd, Oceanwide's contractors will begin assembling test panels on site for the upcoming shoring work anticipated to start in the near future.

The project's 24-hour construction hotline can be reached at 415-746-9948 if you have any concerns.

Update: March 9, 2017

This Saturday from 8:00 AM - 4:30 PM, Oceanwide's contractors will continue internal work on 50 1st street.

Over the next two weeks, Oceanwide's contractors will continue to prep the site at Mission and 1st Street. This work will take place during regular work hours and will include mobilizing equipment for future work.

Jessie Street between Ecker and First Street will be closed daily from 7:00 AM - 5:00 PM to ensure everyone's safety during demolition.

Please call the 24-hour construction hotline 415-746-9948 if you have any concerns.

Update: March 3, 2017

Demolition of 50 First Street will continue into May. This weekend, Oceanwide's contractors will be working in building 50 between 7:00 AM - 5:30 PM on Saturday and 8:00 AM - 5:30 PM on Sunday. Please expect to feel vibrations in nearby buildings.

Starting later this month, vehicular traffic will be rerouted down Ecker between Jessie and Mission as demolition continues along First Street. This reroute will remain until the project is near completion and this portion of Ecker is converted back into a pedestrian-only walkway. At no time during the project will vehicular traffic pass on the section of Ecker between Stevenson and Jessie and that will remain for pedestrian access only.

Site prep work will continue in the Mission Street lot, located on Mission at Ecker. This will continue for the next several weeks.

Please call the 24-hour construction hotline 415-746-9948 if you have any concerns.

Update: February 1, 2017

Starting the week of February 6th, Oceanwide Center will be completing the final test shafts for its foundation which will require some additional night work.

Additional crane equipment will be mobilized as the buildings along First Street continue to be demolished. Jessie Street between Ecker and First Street will be closed daily from 7am - 5pm to ensure everyone’s safety during demolition. Utility work and pedestrian safety improvements will continue on the portion of Ecker between Mission and Jessie for the next several weeks and additional sewer upgrade work will continue along First Street in the evenings.

Update: January 23, 2017

Beginning the week of January 12th, Oceanwide and its authorized contractors began work on the southern portion of Ecker Street between Mission and Jessie Streets. This work includes planned pedestrian improvements and safety upgrades. Jessie Street will continue to be closed during construction hours for the next 4-6 weeks. Beginning January 16th and continuing for a period of three weeks, drilled pile work will be performed 24 hours per day.

24 Hour Construction Hotline to be used in emergencies: (415) 746-9948.

Update: January 6, 2017

Demolition will continue in buildings along First Street. This work will require large equipment to be moved on and off site during work hours.

Jessie Street will continue to be closed during construction hours for the next 4-6 weeks. Continuing through early-mid January, foundation contractors will mobilize equipment for drilling test piles into the ground at 526 Mission. Beginning mid to late January and continuing for a period of three weeks, drilled pile work will be performed 24 hours a day.

Update: November 18, 2016

A majority of the work on Ecker has wrapped up. The utility rerouting where Ecker Street meets Jessie is still being finalized. The final portion of the utility work is expected to be completed the week after Thanksgiving.

Work is expected to begin on the Southern part of Ecker Street, between Mission and Jessie this week. There will be activity in this area between now and November 23rd, including weekend work. The permits allow for work from 7:00 AM to 5:00 PM, 7 days a week but loud work will not begin earlier than 8:00 AM on weekends.

Update: October 14, 2016

Beginning this week, excavation work for utility relocation will begin on the northern part of Ecker Street near Stevenson, heading south down Ecker. The permits allow for work from 7:00AM - 5:00PM, 7 days a week. Loud work will not begin earlier than 8:00am on weekends and holidays. This work is expected to be completed by November 15th.

Demolition of 62 First Street will continue next week with work hours from 7:00am - 5:00pm Monday through Friday.

The sidewalk on the south side of Jessie Street will continue to be closed to pedestrians for the next several months while it is covered with scaffolding.

Update: October 7, 2016

Beginning within the next 10 business days, there will be work commencing on the southern part of Ecker street between Mission Street and Jessie. The activity will include trenching and telecommunications piping improvements.

As early as today, the utility relocation construction team will reach the corner of Ecker and Stevenson; they will begin heading down Ecker street at that time. There will be a 4'10" pedestrian walkway on the One Ecker side of Ecker Street.

Update: September 26, 2016

We wish to keep our tenants updated on the neighboring Oceanwide Project construction where the project is already underway. This new development consists of two towers: one on First Street and the other on Mission Street. Please note that the timeline below is subject to change per city requirements or ordinances.

  • Beginning September 19th into mid-October, site utility relocation work will be taking place on Stevenson Street between First Street and Ecker Street. Work hours are 7:00am - 5:00pm.
  • The utility work is scheduled to turn down Ecker from Stevenson beginning early October through mid-November. Work hours are 7:00am - 5:00pm.
  • Beginning Monday, September 26th and continuing for several months, the south sidewalk on Jessie Street will be closed to pedestrians and covered with scaffolding.
  • Also beginning Monday, September 26th, demolition for 62 First Street is set to begin and is permitted for work from 7:00am - 7:00pm, 7-days a week.

We don’t anticipate this to affect 525 Market Street’s building access or operations. This is only informational. As a general courtesy we will continue to provide updates as we are advised.

 

 